Project

PFK Main Plant & Urea Export Terminal

Area: UET & Main Plant Conveyor Belt System

Total Surface Area: 23,000 m²:

  • UET Phase 1–3 (2015–2019): 17,000 m²
  • Main Plant Conveyor Belt System (2019): 6,000 m²

Surface Preparation:

  • Methods Used: High-Pressure Water Jetting (HPWJ) and St3 (hand and power tool cleaning)
  • Reason: Urea-rich environment required non-abrasive methods to avoid contamination and ensure safety.

Cost Savings:

  • Achieved: 35% savings
  • Reason: No blasting media needed, and faster project completion reduced costs.

Time Reduction:

  • Main Plant Conveyor: Project completed 85 days faster due to efficient methods and streamlined processes.