Project | Details |
Area | Dehydration Module |
Surface Area | 15,000 m² |
Completion Time | 170 days (Dec 08 – May 09) |
Surface Preparation | HPWJ & Power Tools (St3) |
Cost Savings | 30% (RM4.9 M vs RM7.1 M) |
Time Reduction | 280 days (170 days vs 450 days) |
Coating Breakdown | 9% after 10 years |
Annual Coating Degradation | 1% on average |
Inspections | – 10-year Inspection: Oct 2019 – 13-year Inspection: Jul 2022 |
Project
CHOC CAKERAWALA CPP