Project

CHOC CAKERAWALA CPP

Project Details
Area Dehydration Module
Surface Area 15,000 m²
Completion Time 170 days (Dec 08 – May 09)
Surface Preparation HPWJ & Power Tools (St3)
Cost Savings 30% (RM4.9 M vs RM7.1 M)
Time Reduction 280 days (170 days vs 450 days)
Coating Breakdown 9% after 10 years
Annual Coating Degradation 1% on average
Inspections – 10-year Inspection: Oct 2019
– 13-year Inspection: Jul 2022